The CoMPAS roadmap is based on the CoMPAS product vision and the CoMPAS mission and related objectives.
Objectives
Theme | Now | Next | Later |
---|---|---|---|
Please note that CoMPAS heavily relies on OpenSCD for the front-end and manual editing.
Committed:
More basic features
IED services
SCD generation
Better plug-in architecture (OpenSCD-core initiative)
CoMPAS-SCT libary
Idea's for the future:
Modbus support
61850 gateway support (61850-90-2)
More easy SCL checking
Workflow support
Single line editor
Substation logic
Integration SCD generation into front-end
(API) Service for protection settings and measurements
HMI generation (61850-6-2)
Substation logic (IEC 61850-90-11)
User rights
Functional block | Priority rank | Comment |
CoMPAS-SCT libary | 1 | Improve library with the ability to fully generate a substation |
CoMPAS automated generation process | ||
Integrast CoMPAS-SCT with front-end | Collaboration possible with RTE and Alliander | |
SCL validation with schematron | Work in progress | |
Schedulingnodes support | ||
SCL file reports of testing purposes | ||
Idea's for future development:
Modbus support
(API) Service for protection settings and measurements
HMI generation (61850-6-2)
Substation logic (IEC 61850-90-11)
User rights
Code Development Processes
Initial Roadmap Presentation
The initial roadmap of the project was drafted by a design team involving several grid operators and T&D automation vendors:
Roadmap status July 2022
Functional block / workstream | Priority rank | Comment |
Reference architecture | 1 | Done, see: CoMPAS Architecture (com-pas.github.io) |
System Configuration | 1 | Partly possible with manual steps |
Testing | 2 | Work in progress |
IEC61850-CIM mapping | 2 | Done |
System specification | 3 | Done |
Profiling | 3 | Done |