Per the Annual Review process, the TAC will review each hosted project on an annual basis. Below is the schedule for those reviews.
Project | Current Level | Initially Accepted | Last Review Date | Next Review Date |
---|---|---|---|---|
GXF | Early Adoption | February 4, 2020 | October 12, 2021 | October 4, 2022 |
PowSyBl | Early Adoption | April 30, 2019 | August 31, 2021 | August 23, 2022 |
OperatorFabric | Early Adoption | April 30, 2019 | July 20, 2021 | July 12, 2022 |
OpenEEmeter | Incubation | June 4, 2019 | October 12, 2021 | September 13, 2022 |
CoMPAS | Incubation | May 5, 2020 | June 29, 2021 | July 12, 2022 |
OpenLEADR | Incubation | September 15, 2020 | November 23, 2021 | |
SEAPATH | Incubation | October 6, 2020 | November 2, 2021 | |
Hyphae | Incubation | December 8, 2020 | December 14, 2021 | |
SOGNO | Early Adoption | October 27, 2020 | March 16, 2021 | March 8, 2022 |
FledgePOWER | Incubation | February 11, 2021 | February 15, 2022 | |
Grid Capacity Map | Incubation | April 27, 2021 | April 19, 2022 | |
Shapeshifter | Incubation | April 6, 2021 | March 29, 2022 | |
OpenSTF | Incubation | September 21, 2021 | September 13, 2022 | |
EVerest | Sandbox | October 12, 2021 | November 15, 2022 | |
Green Data Hub | Incubation | October 12, 2021 | October 25, 2022 |