This working group focusses on the communication between the charging station (EVerest) and the management system(s) (CPMS)


...

Meeting Notes:

6 September 2024

Development Update:

update on #745 → no issue on the PR, review done soon

#760 - still under discussion, some input from Piet

#727 PR still, Kai to review, first impression good to go

Issue #770 - root cause unknown, debug still ongoing

Discussion:

Daniel Moore → 2.1. is now out
WG should align on a implementation plan
→ Discuss implications in a separate meeting
→ Schedule a focussed meeting in 2-3 weeks for 2.1. TODO Robert

Daniel Moore → Approach to use cases translating into business logic
Following the discussion from Zulip - profiles should be stored or not - how to handle external constraints in composite schedules - and how to implement that in EVerest core - discussion ongoing


28 August 2024

- OCPP 2.1 draft 1 public review start next week. OCPP 2.1 draft available to everybody, excluding the schema files. EVerest has gotten an excempt, we are allowed to share the 2.1 draft schema files with developers working on EVerest. As long as we promise to migrate to production schema files as soon as they are available.

...